					 Oakland Measure DD Bond Public Access 
					Waterfront Projects
  
		 In November 2002, over 80% of Oakland voters passed 
		Measure DD, a $198.25 million bond measure focused on waterfront 
		improvements at Lake Merritt and the Estuary.  Funded projects 
		include parks, trails, bridges, a recreation center, historic building 
		renovations, land acquisition, and creek restoration.  Though these 
		projects are being phased in over a number of years, some are already 
		complete and many others are in progress. From the 
		
		five major categories of 
		Measure DD projects, for this map we have selected projects
		focused on public access to the shoreline:
 
		Completed Projects:
  Pergola Restoration at Lake Merritt 
  Union Point Park 
  Cryer Site Extension of Union Point Park 
  Bay Trail Segment: Alameda Avenue 
  Bay Trail Segment: Fruitvale - High St. 
		gap closure 
  66th Avenue Gateway 
  East 18th St. Pier Restoration 
  Lake Merritt Municipal Boathouse 
		Restoration 
  Lakeside Park Sailboat House Renovation & Restoration 
		(phase1) 
  Lakeside Park Sailboat House Renovation & Restoration 
		(phase2) 
  Derby / Lancaster Pocket Parks 
  Lake Merritt Trail Improvements 
  Lake Merritt Retaining Wall Restoration & Repair 
  12th St. Reconstruction & Park 
  Lakeside Green Streets 
		Projects under construction:
  Lake Merritt Channel Improvements 
					at 10th St. 
 
		Projects awaiting permits, funding supplements, negotiations, 
		etc:
  Lake Merritt Channel Improvements 
		at 7th St. 
  Estuary Bay Trail 
		Connections 
  Estuary Park 
  Crowley Site at Brooklyn Basin 
  Bay Trail Around 3 Bridges to Alameda 
 
		These selected Measure DD projects are shown on the map as blue dots:
  
		For a full picture of all Measure DD projects, including those not directly 
		on the waterfront, please visit: 
						
						 Waterfront Action's 
						Oakland Measure DD Progress Map 
  the
						City of Oakland Measure DD Projects Page 